South Africa’s Medupi Power Station is up and running
24 August 2015
For the first time since construction began eight years ago, the Medupi Power
Station in Limpopo is finally pumping power. The first unit of Medupi, unit six, was
handed over to its operating division on Sunday, 23 August.
Unit six will feed 794 megawatts (MW) of power into the national grid. The unit has
been online since March, but it has been undergoing testing for the past five
months. The first unit was projected to go online in 2011.
Although unit six is pumping enough power to serve a city the size of Bloemfontein,
Eskom spokesperson Khulu Phasiwe said that it did not mean the end of load
shedding.
In an interview with eNews Africa Channel, Phasiwe said the unit would help Eskom
to reduce the risk of load shedding; however, this did not mean load shedding
would end. "In the past two weeks we have not had load shedding and the biggest
contributor to this was the new unit and reduced consumption."
The
contractors had been working on unit six for the past seven years.
According to news reports, Medupi has been contributing almost 800MW to the
power grid since March in an effort to alleviate load shedding. "This power is not a
thoroughly new power per say. It is power that we have been using all along," said
Phasiwe.
On average, South Africa demanded 29 000MW, said Phasiwe. In its current
state, Medupi takes national generation capacity from 42 800MW to
43 600MW.
Five more units still have to be brought online, each generating 794MW. Eskom
plans to have all six units fully functional by 2019. Once complete, Medupi will be
one of the biggest coal power stations in the world.
In July, City Press reported that the government estimated the overall cost of the
station to be at least R105-billion. However, the newspaper added independent
analysts believed the entire project would come up to R300-billion, which was 10
times the original amount
when the contract for the power station was signed.
The Medupi site covers 883 hectares and the highest point of the plant, the
chimneys, will reach 220m. When complete, Medupi will be the fourth-largest coal
power station in the southern hemisphere, and the largest dry-cooled coal power
station in the world.
SAinfo reporter