Seacom cable online 'by June 2009'
Laying cables
The laying of shore-end cables – the cable portions at shallow depths ranging from 15 to 50 metres, where large vessels cannot operate – will commence in September. From October onwards, the first of three Reliance Class vessels will start laying the actual cable. The cable, including repeaters necessary to amplify the signal, will be stored in large tanks onboard the ships, while the branching units necessary to divert the cable to the planned landing stations will be connected into the cable path on the ship just prior to deployment into the sea. The cable will then be buried under the ocean bed with the help of a plough along the best possible route demarcated through the marine survey.System test
The final splicing, which involves connecting all the cable sections together, is scheduled for April 2009, allowing for enough time to test the system before its commercial launch in June 2009. Seacom is also currently also trying to expedite the cable construction in an attempt to assist with the broadcasting requirements of the Fifa Confederations Cup, which South Africa will host in June 2009. "The recently announced executive appointments combined with the project management capabilities already existent within Seacom position us as a fully fledged telecoms player," Herlihy said. "We are able to meet the African market's urgent requirements for cheap and readily available bandwidth within less than a year." SAinfo reporter
or on your website?
See: Using SAinfo material

Related links
Related articles
- West African cable on track for 2010
- Neotel introduces consumer services
- SA research network now online
- New state network goes online
- 3G cards gaining on WiFi spots
- Seacom cable construction begins
- Cheaper broadband on the way
- MTN to build fibre-optic backbone
- South African web use surges
- SA's broadband usage to double